IVR0613

Effective Start Date greater than Current Date plus six months



Submission: SDEM
Status: Active
Severity: Fatal
Input Validation: X
Data Discrepancy: N/A


ACTIVE DEFECTS:

None

ERROR DESCRIPTION:

Effective Start Date must be less than or equal to current date plus six months

FIELDS VALIDATED:

  • 7.04 - Effective Start Date

SUGGESTED RESOLUTION:

Understanding the Error:

The system is trying to ensure that future SINF records are limited to only 6 months based on current date.

Things to check in the submission: Verify that Effective Start Date isn't greater than six months based on current date.

Suggested Resolution:

Change the Effective Start Date to the accurate date(s) and sequence to resolve this error.

NOTES:

N/A

UPDATE:

1/2023 - Added to SDEM

ADDITIONAL INFORMATION:

None



Need more help?

Let's start the conversation by filling out the CALPADS Service Request Form.